sch_new | R Documentation |
Create a new schedule without any information. The new schedule contains the structure to include activities and relations.
sch_new()
A list with schedule definition.
sch_reference()
, sch_add_activities()
, sch_duration()
,
sch_xy_gantt_matrix()
, sch_plan()
, sch_add_relations()
,
sch_validate()
, sch_non_critical_activities()
, sch_title()
.
sch <- sch_new() %>% sch_add_activities( id = c(1L, 2L, 3L, 4L), name = c("A", "B", "C", "D"), duration = c(3L, 4L, 9L, 1L) ) %>% sch_add_relations( from = c(1L, 2L, 2L), to = c(2L, 3L, 4L) ) %>% sch_plan() sch_duration(sch) # 16