sch_plan | R Documentation |
Perform schedule plan: execute topological sort and critical path calculation. All information about critical path are calculated.
sch_plan(sch)
sch |
A schedule object. |
A schedule with critical path calculated.
sch_gantt_matrix()
, sch_duration()
, sch_reference()
,
sch_add_activities()
, sch_has_any_activity()
, sch_title()
, sch_new()
,
sch_add_relations()
.
sch <- sch_new() %>% sch_add_activities( id = c(1L, 2L, 3L, 4L), name = c("A", "B", "C", "D"), duration = c(3L, 4L, 9L, 1L) ) %>% sch_add_relations( from = c(1L, 2L, 2L), to = c(2L, 3L, 4L) ) %>% sch_plan() sch_duration(sch) # 16