sch_new: New Schedule

Description Usage Value See Also Examples

View source: R/sch_schedule.R

Description

Create a new schedule without any information. The new schedule contains the structure to include activities and relations.

Usage

1

Value

A list with schedule definition.

See Also

sch_reference(), sch_add_activities(), sch_duration(), sch_xy_gantt_matrix(), sch_plan(), sch_add_relations(), sch_validate(), sch_non_critical_activities(), sch_title().

Examples

 1
 2
 3
 4
 5
 6
 7
 8
 9
10
11
12
sch <- sch_new() %>%
  sch_add_activities(
    id = c(1L, 2L, 3L, 4L),
    name = c("A", "B", "C", "D"),
    duration = c(3L, 4L, 9L, 1L)
  ) %>%
  sch_add_relations(
    from = c(1L, 2L, 2L),
    to   = c(2L, 3L, 4L)
  ) %>%
  sch_plan()
sch_duration(sch) # 16

rubens2005/criticalpath documentation built on Feb. 6, 2022, 10:54 p.m.