vanhoucke_2009_p18 <- function() {
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 1L, "a1" , 0L, 2,3,4) %>%
sch_add_activity( 2L, "a2" , 4L, 5) %>%
sch_add_activity( 3L, "a3" , 9L, 10) %>%
sch_add_activity( 4L, "a4" , 1L, 6) %>%
sch_add_activity( 5L, "a5" , 4L, 9) %>%
sch_add_activity( 6L, "a6" , 5L, 7) %>%
sch_add_activity( 7L, "a7" , 1L, 8, 11) %>%
sch_add_activity( 8L, "a8" , 7L, 12) %>%
sch_add_activity( 9L, "a9" , 8L, 12) %>%
sch_add_activity( 10L, "a10", 3L, 12) %>%
sch_add_activity( 11L, "a11", 3L, 12) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
return(sch)
}
test_that("Creating a sch step-by-step, with activities and relations together", {
sch <- vanhoucke_2009_p18()
atb <- sch_activities(sch)
expect_equal(sch_duration(sch), 16)
expect_equal(atb$early_start[1], 0)
expect_equal(atb$early_finish[1], 0)
expect_equal(atb$late_start[1], 0)
expect_equal(atb$late_finish[1], 0)
expect_true(atb$critical[1])
expect_equal(atb$early_start[2], 0)
expect_equal(atb$early_finish[2], 4)
expect_equal(atb$late_start[2], 0)
expect_equal(atb$late_finish[2], 4)
expect_true(atb$critical[2])
expect_equal(atb$early_start[3], 0)
expect_equal(atb$early_finish[3], 9)
expect_equal(atb$late_start[3], 4)
expect_equal(atb$late_finish[3], 13)
expect_false(atb$critical[3])
expect_equal(atb$early_start[4], 0)
expect_equal(atb$early_finish[4], 1)
expect_equal(atb$late_start[4], 2)
expect_equal(atb$late_finish[4], 3)
expect_false(atb$critical[4])
expect_equal(atb$early_start[5], 4)
expect_equal(atb$early_finish[5], 8)
expect_equal(atb$late_start[5], 4)
expect_equal(atb$late_finish[5], 8)
expect_true(atb$critical[5])
expect_equal(atb$early_start[6], 1)
expect_equal(atb$early_finish[6], 6)
expect_equal(atb$late_start[6], 3)
expect_equal(atb$late_finish[6], 8)
expect_false(atb$critical[6])
expect_equal(atb$early_start[7], 6)
expect_equal(atb$early_finish[7], 7)
expect_equal(atb$late_start[7], 8)
expect_equal(atb$late_finish[7], 9)
expect_false(atb$critical[7])
expect_equal(atb$early_start[8], 7)
expect_equal(atb$early_finish[8], 14)
expect_equal(atb$late_start[8], 9)
expect_equal(atb$late_finish[8], 16)
expect_false(atb$critical[8])
expect_equal(atb$early_start[9], 8)
expect_equal(atb$early_finish[9], 16)
expect_equal(atb$late_start[9], 8)
expect_equal(atb$late_finish[9], 16)
expect_true(atb$critical[9])
expect_equal(atb$early_start[10], 9)
expect_equal(atb$early_finish[10], 12)
expect_equal(atb$late_start[10], 13)
expect_equal(atb$late_finish[10], 16)
expect_false(atb$critical[10])
expect_equal(atb$early_start[11], 7)
expect_equal(atb$early_finish[11], 10)
expect_equal(atb$late_start[11], 13)
expect_equal(atb$late_finish[11], 16)
expect_false(atb$critical[11])
expect_equal(atb$early_start[12], 16)
expect_equal(atb$early_finish[12], 16)
expect_equal(atb$late_start[12], 16)
expect_equal(atb$late_finish[12], 16)
expect_true(atb$critical[12])
})
test_that("Creating a sch step-by-step, with activities and relations together: float tests", {
sch <- vanhoucke_2009_p18()
atb <- sch_activities(sch)
expect_equal(atb$total_float[1], 0)
expect_equal(atb$total_float[2], 0)
expect_equal(atb$total_float[3], 4)
expect_equal(atb$total_float[4], 2)
expect_equal(atb$total_float[5], 0)
expect_equal(atb$total_float[6], 2)
expect_equal(atb$total_float[7], 2)
expect_equal(atb$total_float[8], 2)
expect_equal(atb$total_float[9], 0)
expect_equal(atb$total_float[10], 4)
expect_equal(atb$total_float[11], 6)
expect_equal(atb$total_float[12], 0)
})
test_that("Does not return Inf!!!", {
# Create a sch
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 2L, "a2" , 4L, 5) %>%
sch_add_activity( 3L, "a3" , 9L, 10) %>%
sch_add_activity( 4L, "a4" , 1L, 6) %>%
sch_add_activity( 5L, "a5" , 4L, 9) %>%
sch_add_activity( 6L, "a6" , 5L, 7) %>%
sch_add_activity( 7L, "a7" , 1L, 8,11) %>%
sch_add_activity( 8L, "a8" , 7L, 12) %>%
sch_add_activity( 9L, "a9" , 8L, 12) %>%
sch_add_activity( 10L, "a10", 3L, 12) %>%
sch_add_activity( 11L, "a11", 3L, 12) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
expect_true(all(!is.infinite(sch$activities$late_start)))
expect_true(all(!is.infinite(sch$activities$late_finish)))
expect_true(all(!is.na(sch$activities$late_start)))
expect_true(all(!is.na(sch$activities$late_finish)))
expect_equal(sch_duration(sch), 16)
id <- 2
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 0)
expect_equal(atv$early_finish, 4)
expect_equal(atv$late_start, 0)
expect_equal(atv$late_finish, 4)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 3
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 0)
expect_equal(atv$early_finish, 9)
expect_equal(atv$late_start, 4)
expect_equal(atv$late_finish, 13)
expect_equal(atv$total_float, 4)
expect_equal(atv$free_float, 0)
id <- 4
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 0)
expect_equal(atv$early_finish, 1)
expect_equal(atv$late_start, 2)
expect_equal(atv$late_finish, 3)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 5
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 4)
expect_equal(atv$early_finish, 8)
expect_equal(atv$late_start, 4)
expect_equal(atv$late_finish, 8)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 6
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 1)
expect_equal(atv$early_finish, 6)
expect_equal(atv$late_start, 3)
expect_equal(atv$late_finish, 8)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 7
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 6)
expect_equal(atv$early_finish, 7)
expect_equal(atv$late_start, 8)
expect_equal(atv$late_finish, 9)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 8
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 7)
expect_equal(atv$early_finish, 14)
expect_equal(atv$late_start, 9)
expect_equal(atv$late_finish, 16)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 2)
id <- 9
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 8)
expect_equal(atv$early_finish, 16)
expect_equal(atv$late_start, 8)
expect_equal(atv$late_finish, 16)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 10
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 9)
expect_equal(atv$early_finish, 12)
expect_equal(atv$late_start, 13)
expect_equal(atv$late_finish, 16)
expect_equal(atv$total_float, 4)
expect_equal(atv$free_float, 4)
id <- 11
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 7)
expect_equal(atv$early_finish, 10)
expect_equal(atv$late_start, 13)
expect_equal(atv$late_finish, 16)
expect_equal(atv$total_float, 6)
expect_equal(atv$free_float, 6)
id <- 12
atv <- sch_get_activity(sch, id)
expect_equal(atv$early_start, 16)
expect_equal(atv$early_finish, 16)
expect_equal(atv$late_start, 16)
expect_equal(atv$late_finish, 16)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
})