# Mon May 7 11:41:11 PDT 2018
#
# This is a direct implementation of Sinnen's definitions in 'Task
# Scheduling for parallel Systems'
#
# I'll try to adhere to the convention that 'time' refers to the relative
# timeline starting with the beginning of the computation at 0, and 'cost'
# means an absolute time required to do some smaller step.
#' Minimize Expression Start Time
#'
#' Implementation of "list scheduling".
#' This is a greedy algorithm that assigns each expression to the earliest
#' possible processor.
#'
#' This function is experimental and unstable. If you're trying to actually
#' speed up your code through parallelism then consider using the default
#' method in \code{\link{schedule}} for data parallelism.
#' This function rewrites code to use task parallelism.
#' Task parallelism means two or more processors run different R
#' expressions simultaneously.
#'
#' @references Algorithm 10 in \emph{Task Scheduling for Parallel
#' Systems}, Sinnen (2007)
#'
#' @export
#' @param graph object of class \code{DependGraph} as returned from \code{\link{inferGraph}}
#' @param maxWorker integer maximum number of processors
#' @param exprTime time in seconds to execute each expression
#' @param exprTimeDefault numeric time in seconds to execute a single
#' expression. This will only be used if \code{exprTime} is NULL.
#' @param sizeDefault numeric default size of objects to transfer in bytes
#' @param overhead numeric seconds to send any object
#' @param bandwidth numeric speed that the network can transfer an object
#' between processors in bytes per second. We don't take network
#' contention into account. This will have to be extended to account for
#' multiple machines.
#' @return schedule object of class \code{TaskSchedule}
#' @examples
#' code <- parse(text = "a <- 100
#' b <- 200
#' c <- a + b")
#'
#' g <- inferGraph(code)
#' s <- scheduleTaskList(g)
#' plot(s)
scheduleTaskList = function(graph, maxWorker = 2L
, exprTime = NULL
, exprTimeDefault = 10e-6
, sizeDefault = as.numeric(utils::object.size(1L))
, overhead = 8e-6
, bandwidth = 1.5e9
){
procs = seq(maxWorker)
nnodes = length(graph@code)
tg = graph@graph
# TODO:* use expression times from MeasuredDependGraph
if(is.null(exprTime)){
exprTime = rep(exprTimeDefault, nnodes)
}
if(!("size" %in% colnames(tg))){
tg[, "size"] = sizeDefault
}
# Initialize by scheduling the first expression on the first worker.
schedule = list(
eval = data.frame(processor = 1L
, start_time = 0
, end_time = exprTime[1]
, node = 1L
),
transfer = data.frame(start_time_send = numeric()
, start_time_receive = numeric()
, end_time_send = numeric()
, end_time_receive = numeric()
, proc_send = integer()
, proc_receive = integer()
, varname = character()
, stringsAsFactors = FALSE
))
# It would be easier if we know every variable that every worker has
# after every expression and transfer. Then we could see what they
# need, and where they can possibly get them. SSA could help by
# eliminating duplicated variable names. For the moment I will assume
# the variable names are unique.
for(node in seq(2, nnodes)){
allprocs = lapply(procs, data_ready_time
, node = node, graph = tg, schedule = schedule
, overhead = overhead, bandwidth = bandwidth
)
start_times = sapply(allprocs, `[[`, "time")
# Pick the winner, choosing lower numbers in ties
earliest_proc = which.min(start_times)
# Update schedule with necessary transfers
schedule = allprocs[[earliest_proc]]$schedule
schedule = schedule_node(earliest_proc
, node = node, schedule = schedule
, node_time = exprTime[node]
)
}
new("TaskSchedule", graph = graph
, evaluation = schedule$eval
, transfer = schedule$transfer
, maxWorker = as.integer(maxWorker)
, exprTime = exprTime
, overhead = overhead
, bandwidth = bandwidth
)
}
# Which Processor Is Assigned to this node in the schedule?
which_processor = function(node, schedule)
{
e = schedule$eval
e[e$node == node, "processor"]
}
data_ready_time = function(proc, node, graph, schedule, overhead, bandwidth)
{
# Transfer from predecessors to current node
preds = predecessors(node, graph)
# Not sure we need this
# No predecessors
#if(length(preds) == 0L){
# return(proc_finish_time(proc, schedule))
#}
other_procs = sapply(preds, which_processor, schedule)
# Let the processors that aren't busy start transferring first
busy_last = order(sapply(other_procs, proc_finish_time, schedule))
preds = preds[busy_last]
other_procs = other_procs[busy_last]
# Update the schedule
for(p in preds){
schedule = add_send_receive(proc, node_from = p, node_to = node
, graph = graph, schedule = schedule
, overhead = overhead, bandwidth = bandwidth
)
}
# Now the node is ready to run on proc
# Pass the updated schedule along so we don't need to compute it again.
list(time = proc_finish_time(proc, schedule), schedule = schedule)
}
# Time to transfer required data between nodes
# Def 4.4 p. 77
# This is the place to include models for latency.
# @param tg_row is a single row from a task graph
transfer_cost = function(tg_row, overhead, bandwidth)
{
if(nrow(tg_row) > 1) stop("Did not expect multiple transfers here.")
tg_row[, "size"] / bandwidth + overhead
}
# Time when the processor has finished all scheduled tasks
proc_finish_time = function(proc, schedule)
{
t_eval = schedule$eval[schedule$eval$processor == proc, "end_time"]
trans = schedule$transfer
t_send = trans[trans$proc_send == proc, "end_time_send"]
t_receive = trans[trans$proc_receive == proc, "end_time_receive"]
max(t_eval, t_send, t_receive, 0)
}
# The nodes which must be completed before node can be evaluated
predecessors = function(node, graph)
{
unique(graph[graph$to == node, "from"])
}
# Account for the constraint from one node to another, and return an
# updated schedule.
add_send_receive = function(processor, node_from, node_to, graph, schedule
, overhead, bandwidth)
{
# TODO: This will probably break if we evaluate the same node multiple
# times, but that's a future problem.
from = schedule$eval[schedule$eval$node == node_from, ]
proc_receive = processor
proc_send = from$processor
# If both nodes are already on the same processor then the data / state
# is available and this function is a non op.
if(proc_send == proc_receive){
return(schedule)
}
# One expression can define multiple variables simultaneously, ie.
# a = b = 5
tg_from_to = graph[(graph$from == node_from) & (graph$to == node_to), ]
for(i in seq(nrow(tg_from_to))){
schedule = add_single_send_receive(tg_from_to[i, ], schedule
, proc_send, proc_receive
, overhead, bandwidth)
}
schedule
}
add_single_send_receive = function(tg_from_to, schedule
, proc_send, proc_receive
, overhead, bandwidth)
{
start_time_send = proc_finish_time(proc_send, schedule)
tc = transfer_cost(tg_from_to, overhead, bandwidth)
# TODO: Hardcoding in 0 latency here and other places. Will need to fix
# this when running on actual distributed machines.
start_time_receive = max(proc_finish_time(proc_receive, schedule), start_time_send)
this_transfer = data.frame(start_time_send = start_time_send
, end_time_send = start_time_send + tc
, start_time_receive = start_time_receive
, end_time_receive = start_time_receive + tc
, proc_send = proc_send
, proc_receive = proc_receive
, varname = tg_from_to[, "value"]
, stringsAsFactors = FALSE
)
schedule$transfer = rbind(schedule$transfer, this_transfer)
schedule
}
# Assign node to processor as the last step in the schedule, and
# return the updated schedule. All dependencies in the task graph should
# be satisfied at this point.
schedule_node = function(processor, node, schedule, node_time)
{
start_time = proc_finish_time(processor, schedule)
this_task = data.frame(processor = processor
, start_time = start_time
, end_time = start_time + node_time
, node = node
)
schedule$eval = rbind(schedule$eval, this_task)
schedule
}