Description Usage Arguments Examples
Computes the time (or cost) required for a specific unit using Wright's cumulative average model.
1 |
t |
time (or cost) required for the mth unit of production |
n |
nth unit you wish to predict the time (or cost) for |
r |
learning curve rate |
m |
mth unit for which you have time (or cost) information (default is m = 1) |
na.rm |
Should |