Description Usage Arguments Examples
Provides the exact cumulative time or cost required for units m through n (inclusive) using the Crawford unit model
1 | unit_cum_exact(t, n, r, m = 1, na.rm = FALSE)
|
t |
time (or cost) required for the mth unit of production |
n |
The unit you wish to predict the cumulative time (or cost) to |
r |
learning curve rate |
m |
mth unit of production (default set to 1st production unit) |
na.rm |
Should |
1 2 3 4 5 6 7 8 | library(learningCurve)
# An estimator believes that the first unit of a product will
# require 100 labor hours. How many total hours will be required
# for 125 units given the organization has historically experienced
# an 85% learning curve?
unit_cum_exact(t = 100, n = 125, r = .85)
## [1] 5201.085
|