testthat::context("Wrangle")
logger::log_threshold(logger::FATAL, namespace = "projectPlan")
test_that(
"Conversion of numeric dates", {
expect_equal(h.convert_numeric_date(letters[1:3], date_origin = "1899-12-30"), letters[1:3])
expect_equal(h.convert_numeric_date(rep(NA_character_, 3), date_origin = "1899-12-30"), rep(NA_character_, 3))
expect_equal(h.convert_numeric_date(c("43529", "43530"), date_origin = "1899-12-30"), c("2019-03-05", "2019-03-06"))
})
d_in <- data.table::data.table(depends_on = c("A"), start = c("TODAY"))
d_expected <- data.table::data.table(depends_on = c("A"), start = as.character(NA), fixed_start_date = lubridate::as_date(lubridate::now()))
test_that(
"TODAY becomes the current date",
expect_equal(h.rd_preprocess_start_column(d_in, date_origin = "1899-12-30"), d_expected)
)
d_in <- data.table::data.table(depends_on = c("A"), start = c(NA))
d_expected <- data.table::data.table(depends_on = c("A"), start = as.character(NA), fixed_start_date = lubridate::as_date(NA))
test_that(
"start-column contains only NA",
expect_equal(h.rd_preprocess_start_column(d_in, date_origin = "1899-12-30"), d_expected)
)
d_in <- data.table::data.table(
project = "p", section = "s", id = "i",
depends_on = c(NA, "A"), start = c(NA, "B"))
d_expected <- data.table::data.table(
project = "p", section = "s", id = "i",
depends_on = c(NA, "A"), start = c(NA, "B"), fixed_start_date = c(lubridate::as_date(lubridate::now()), NA))
test_that(
"Current date is default if no dependency and no start is defined",
expect_equal(h.rd_preprocess_start_column(d_in, date_origin = "1899-12-30"), d_expected)
)
d_in <- data.table::data.table(end = c("2018-09-20", "WAIT", "43530"))
d_expected <- data.table::data.table(
fixed_end_date = c(lubridate::ymd("2018-09-20"), NA, lubridate::ymd("2019-03-06"))
)
test_that(
"ymd and 'numeric' ín -end- are processed correctly", {
expect_equal(h.rd_preprocess_end_column(d_in, date_origin = "1899-12-30"), d_expected)
}
)
d_in <- data.table::data.table(deadline = c("2018-09-20", "2018-10-27"))
d_expected <- data.table::data.table(
deadline = c(lubridate::ymd("2018-09-20"), lubridate::ymd("2018-10-29")),
raw_deadline = c("2018-09-20", "2018-10-27")
)
test_that(
"ymd in -deadline- are processed correctly", {
expect_equal(h.rd_preprocess_deadline_column(d_in, date_origin = "1899-12-30"), d_expected)
expect_error(h.rd_preprocess_deadline_column(data.table::data.table(deadline = "20-09-2018"), date_origin = "1899-12-30"), regexp = "must be.*ymd")
}
)
d_in <- data.table::data.table(
project = "A", id = "I", section = "S",
depends_on = c("a", "a, B::b"),
start = c("b, B::b", "c, d, C::h"),
task = letters[3:4],
resource = letters[5:6],
microtasks = letters[7:8],
comments = letters[9:10],
progress = c(10, 90),
deadline = lubridate::ymd(c("2018-09-20", "2018-09-21")),
fixed_start_date = lubridate::ymd(c("2018-09-10", "2018-09-11")),
fixed_end_date = lubridate::ymd(c("2018-09-15", "2018-09-16")),
est_days = c(2, 3),
waiting = c(F, T),
aborted = c(T, F),
unscheduled = c(T, F)
)
d_expected <- data.table::data.table(
project = "A", id = "A::I",
depends_on = list(c("A::a", "B::b")),
start = list(c("A::b", "A::c", "A::d", "B::b", "C::h")),
prior_ids = list(c("A::a", "A::b", "A::c", "A::d", "B::b", "C::h")),
section = "A::S",
resource = c("e, f"),
task = c("c, d"),
microtasks = c("g, h"),
comments = c("i, j"),
progress = c(50),
deadline = lubridate::ymd(c("2018-09-20")),
fixed_start_date = lubridate::ymd(c("2018-09-10")),
fixed_end_date = lubridate::ymd(c("2018-09-16")),
est_days = c(5),
waiting = c(T),
aborted = c(T),
unscheduled = c(T),
nmb_combined_entries = 2L
)
test_that(
"combine ids within project in order to make them unique", {
expect_equal(h.rd_make_id_unique_within_project(d_in), d_expected)
}
)
d_in <- data.frame(
project = c("A"),
section = NA_character_,
id = c(NA_character_, NA_character_),
depends_on = NA_character_,
start = NA_character_,
end = NA_character_,
est_duration = NA_character_,
status = NA_character_,
resource = NA_character_,
task = NA_character_,
microtasks = NA_character_,
comments = NA_character_,
progress = NA,
deadline = NA_character_,
some_col = "will get lost"
)
d_expected <- data.table::data.table(
project = c("A"),
id = c("A::NOT_SPECIFIED_1", "A::NOT_SPECIFIED_2"),
depends_on = NA_character_,
start = NA_character_,
prior_ids = NA_character_,
section = "A::UNKNOWN",
resource = "UNKNOWN",
task = "UNKNOWN",
microtasks = "-",
comments = "-",
progress = 0,
deadline = lubridate::as_date(NA),
fixed_start_date = lubridate::as_date(lubridate::now()),
fixed_end_date = lubridate::as_date(NA),
est_days = 1,
waiting = FALSE,
aborted = FALSE,
unscheduled = FALSE,
nmb_combined_entries = 1L
)
d_out <- wrangle_raw_plan(d_in)
test_that(
"Complete raw data wrangling. check default values", {
expect_equal(d_out, d_expected)
}
)
d_in <- data.frame(
project = c("A"),
section = c("0_prep"),
id = c("a", "a", "a"),
depends_on = c("b, B::b", "b, b", "B::b"),
start = c("2018-09-10", "2018-09-11", "2018-09-09"),
end = c("2018-09-20", "2018-10-25", "2018-10-01"),
est_duration = c("1", "2", "2"),
status = c("aborted", "await", "unscheduled"),
resource = c("r1, r2", "r2", "r3"),
task = c("t1", "t2", "t3"),
microtasks = c(NA_character_, NA_character_, ".t3_1"),
comments = c("c1", NA_character_, "c3"),
progress = c(0, 50, 70),
deadline = c("2018-09-23", "2018-10-01", "2018-10-02"),
stringsAsFactors = FALSE
)
d_expected <- data.table::data.table(
project = c("A"),
id = "A::a",
depends_on = list(c("A::b", "B::b")),
start = NA_character_,
prior_ids = list(c("A::b", "B::b")),
section = c("A::0_prep"),
resource = c("r1, r2, r3"),
task = c("t1, t2, t3"),
microtasks = c("-, .t3_1"),
comments = c("-, c1, c3"),
progress = c(40),
deadline = lubridate::as_date(c("2018-09-24")),
fixed_start_date = lubridate::as_date(c("2018-09-09")),
fixed_end_date = lubridate::as_date(c("2018-10-25")),
est_days = 5,
waiting = TRUE,
aborted = TRUE,
unscheduled = TRUE,
nmb_combined_entries = 3L,
stringsAsFactors = FALSE
)
d_out <- wrangle_raw_plan(d_in)
test_that(
"Complete raw data wrangling with combining ids", {
expect_equal(d_out, d_expected)
}
)
d_in <- data.table::rbindlist(
list(
data.table::data.table(
project = "A", id = letters[1:3], section = "S",
depends_on = c(NA, "PREVIOUS, xyz", "PREVIOUS"),
start = c("PREVIOUS", NA, NA)
),
data.table::data.table(
project = "B", id = letters[1:3], section = "S",
depends_on = c(NA, "PREVIOUS", NA),
start = c("PREVIOUS, A::a", NA, "PREVIOUS")
)
)
)
d_out_dep <- data.table::rbindlist(
list(
data.table::data.table(
project = "A", id = letters[1:3], section = "S",
depends_on = c(NA, "A::a, xyz", "A::b"),
start = c("PREVIOUS", NA, NA)
),
data.table::data.table(
project = "B", id = letters[1:3], section = "S",
depends_on = c(NA, "B::a", NA),
start = c("PREVIOUS, A::a", NA, "PREVIOUS")
)
)
)
d_out_start <- data.table::rbindlist(
list(
data.table::data.table(
project = "A", id = letters[1:3], section = "S",
depends_on = c(NA, "PREVIOUS, xyz", "PREVIOUS"),
start = c("PREVIOUS", NA, NA)
),
data.table::data.table(
project = "B", id = letters[1:3], section = "S",
depends_on = c(NA, "PREVIOUS", NA),
start = c("A::a, A::c", NA, "B::b")
)
)
)
test_that(
"PREVIOUS tag is replaced correctly", {
expect_equal(h.replace_TAG_PREVIOUS(d_in, "depends_on"), d_out_dep)
expect_equal(h.replace_TAG_PREVIOUS(d_in, "start"), d_out_start)
}
)