vanhoucke_2009_p18 <- function() {
schedule <- Schedule$new()
schedule$title <- "Fictitious Project Example"
schedule$reference <- "VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18"
schedule$add_act_rel( 1, "a1" , 0, c(2,3,4))
schedule$add_act_rel( 2, "a2" , 4, c(5))
schedule$add_act_rel( 3, "a3" , 9, c(10))
schedule$add_act_rel( 4, "a4" , 1, c(6))
schedule$add_act_rel( 5, "a5" , 4, c(9))
schedule$add_act_rel( 6, "a6" , 5, c(7))
schedule$add_act_rel( 7, "a7" , 1, c(8,11))
schedule$add_act_rel( 8, "a8" , 7, c(12))
schedule$add_act_rel( 9, "a9" , 8, c(12))
schedule$add_act_rel( 10, "a10", 3, c(12))
schedule$add_act_rel( 11, "a11", 3, c(12))
schedule$add_act_rel( 12, "a12", 0)
schedule
}
test_that("Creating a schedule step-by-step, with activities and relations together", {
schedule <- vanhoucke_2009_p18()
activities <- schedule$activities
expect_equal(schedule$duration, 16)
expect_equal(activities$ES[1], 0)
expect_equal(activities$EF[1], 0)
expect_equal(activities$LS[1], 0)
expect_equal(activities$LF[1], 0)
expect_true(activities$critical[1])
expect_equal(activities$ES[2], 0)
expect_equal(activities$EF[2], 4)
expect_equal(activities$LS[2], 0)
expect_equal(activities$LF[2], 4)
expect_true(activities$critical[2])
expect_equal(activities$ES[3], 0)
expect_equal(activities$EF[3], 9)
expect_equal(activities$LS[3], 4)
expect_equal(activities$LF[3], 13)
expect_false(activities$critical[3])
expect_equal(activities$ES[4], 0)
expect_equal(activities$EF[4], 1)
expect_equal(activities$LS[4], 2)
expect_equal(activities$LF[4], 3)
expect_false(activities$critical[4])
expect_equal(activities$ES[5], 4)
expect_equal(activities$EF[5], 8)
expect_equal(activities$LS[5], 4)
expect_equal(activities$LF[5], 8)
expect_true(activities$critical[5])
expect_equal(activities$ES[6], 1)
expect_equal(activities$EF[6], 6)
expect_equal(activities$LS[6], 3)
expect_equal(activities$LF[6], 8)
expect_false(activities$critical[6])
expect_equal(activities$ES[7], 6)
expect_equal(activities$EF[7], 7)
expect_equal(activities$LS[7], 8)
expect_equal(activities$LF[7], 9)
expect_false(activities$critical[7])
expect_equal(activities$ES[8], 7)
expect_equal(activities$EF[8], 14)
expect_equal(activities$LS[8], 9)
expect_equal(activities$LF[8], 16)
expect_false(activities$critical[8])
expect_equal(activities$ES[9], 8)
expect_equal(activities$EF[9], 16)
expect_equal(activities$LS[9], 8)
expect_equal(activities$LF[9], 16)
expect_true(activities$critical[9])
expect_equal(activities$ES[10], 9)
expect_equal(activities$EF[10], 12)
expect_equal(activities$LS[10], 13)
expect_equal(activities$LF[10], 16)
expect_false(activities$critical[10])
expect_equal(activities$ES[11], 7)
expect_equal(activities$EF[11], 10)
expect_equal(activities$LS[11], 13)
expect_equal(activities$LF[11], 16)
expect_false(activities$critical[11])
expect_equal(activities$ES[12], 16)
expect_equal(activities$EF[12], 16)
expect_equal(activities$LS[12], 16)
expect_equal(activities$LF[12], 16)
expect_true(activities$critical[12])
})
test_that("Creating a schedule step-by-step, with activities and relations together: float tests", {
schedule <- vanhoucke_2009_p18()
activities <- schedule$activities
expect_equal(activities$total_float[1], 0)
expect_equal(activities$total_float[2], 0)
expect_equal(activities$total_float[3], 4)
expect_equal(activities$total_float[4], 2)
expect_equal(activities$total_float[5], 0)
expect_equal(activities$total_float[6], 2)
expect_equal(activities$total_float[7], 2)
expect_equal(activities$total_float[8], 2)
expect_equal(activities$total_float[9], 0)
expect_equal(activities$total_float[10], 4)
expect_equal(activities$total_float[11], 6)
expect_equal(activities$total_float[12], 0)
})
test_that("Does not return Inf!!!", {
# Create a schedule
schedule <- Schedule$new()
schedule$title <- "Fictitious Project Example"
schedule$reference <- "VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18"
# Add activities and relations to it.
schedule$add_act_rel( 2, "a2" , 4, c(5))
schedule$add_act_rel( 3, "a3" , 9, c(10))
schedule$add_act_rel( 4, "a4" , 1, c(6))
schedule$add_act_rel( 5, "a5" , 4, c(9))
schedule$add_act_rel( 6, "a6" , 5, c(7))
schedule$add_act_rel( 7, "a7" , 1, c(8,11))
schedule$add_act_rel( 8, "a8" , 7, c(12))
schedule$add_act_rel( 9, "a9" , 8, c(12))
schedule$add_act_rel( 10, "a10", 3, c(12))
schedule$add_act_rel( 11, "a11", 3, c(12))
schedule$add_act_rel( 12, "a12", 0)
expect_true(all(!is.infinite(schedule$activities$LS)))
expect_true(all(!is.infinite(schedule$activities$LF)))
expect_true(!is.na(schedule$topoi_sp()))
expect_true(!is.na(schedule$topoi_ad()))
expect_true(!is.na(schedule$topoi_la()))
expect_true(!is.na(schedule$topoi_tf()))
expect_equal(schedule$duration, 16)
id <- 2
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 0)
expect_equal(atv$EF, 4)
expect_equal(atv$LS, 0)
expect_equal(atv$LF, 4)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 3
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 0)
expect_equal(atv$EF, 9)
expect_equal(atv$LS, 4)
expect_equal(atv$LF, 13)
expect_equal(atv$total_float, 4)
expect_equal(atv$free_float, 0)
id <- 4
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 0)
expect_equal(atv$EF, 1)
expect_equal(atv$LS, 2)
expect_equal(atv$LF, 3)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 5
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 4)
expect_equal(atv$EF, 8)
expect_equal(atv$LS, 4)
expect_equal(atv$LF, 8)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 6
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 1)
expect_equal(atv$EF, 6)
expect_equal(atv$LS, 3)
expect_equal(atv$LF, 8)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 7
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 6)
expect_equal(atv$EF, 7)
expect_equal(atv$LS, 8)
expect_equal(atv$LF, 9)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 0)
id <- 8
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 7)
expect_equal(atv$EF, 14)
expect_equal(atv$LS, 9)
expect_equal(atv$LF, 16)
expect_equal(atv$total_float, 2)
expect_equal(atv$free_float, 2)
id <- 9
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 8)
expect_equal(atv$EF, 16)
expect_equal(atv$LS, 8)
expect_equal(atv$LF, 16)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
id <- 10
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 9)
expect_equal(atv$EF, 12)
expect_equal(atv$LS, 13)
expect_equal(atv$LF, 16)
expect_equal(atv$total_float, 4)
expect_equal(atv$free_float, 4)
id <- 11
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 7)
expect_equal(atv$EF, 10)
expect_equal(atv$LS, 13)
expect_equal(atv$LF, 16)
expect_equal(atv$total_float, 6)
expect_equal(atv$free_float, 6)
id <- 12
atv <- schedule$get_activity(id)
expect_equal(atv$ES, 16)
expect_equal(atv$EF, 16)
expect_equal(atv$LS, 16)
expect_equal(atv$LF, 16)
expect_equal(atv$total_float, 0)
expect_equal(atv$free_float, 0)
})