Nothing
#' Calculate the Earned Value of a Project Schedule to Date
#'
#' Given a set of project activities start times, end times, progress and costs,
#' this function calculates the Earned Value at a certain Date
#' @importFrom lubridate today
#' @importFrom zoo na.approx
#' @importFrom dplyr mutate
#' @importFrom rlang .data
#'
#' @param start Start Date of activity
#' @param end End Date of activity
#' @param progress Proportion between 0 and 1 representing percentage completed
#' for each activity (1 = 100% complete)
#' @param planned_cost The planned costs of each activity
#' @param project_value The total value of the project
#' @param cost_to_date The total amount spent on the project to date
#' @param date Character date "YYYY-MM-DD". Defaults to today.
#'
#' @return A list of two data frames:
#' \itemize{
#' \item \strong{pv} Planned Value Schedule, a data frame with two columns:
#' \itemize{
#' \item \strong{date:} Daily Dates over Project Schedule
#' \item \strong{planned_value:} The Planned Value to be delivered at that date.
#' }
#' \item \strong{ev} Earned Value Calculations, a data frame with 15 columns:
#' \itemize{
#' \item \strong{date:} Date of calculation
#' \item \strong{total_value:} Total Value of the Project.
#' \item \strong{budget_at_completion:} Aggregate costs of all of the task
#' budgets
#' \item \strong{project_complete:} Project Complete based on Earned Value and
#' total Project Value.
#' \item \strong{schedule_complete:} The difference in Earned Value and Planned
#' value as a proportion of the Total Value.
#' \item \strong{planned_value:} The amount of the project that is supposed to
#' have been completed.
#' \item \strong{earned_value:} The amount of the project that is actually
#' completed
#' \item \strong{actual_cost:} Actual Cost is the actual to-date cost of the
#' project.
#' \item \strong{schedule_variance:} The amount that the project is ahead or
#' behind schedule.
#' \item \strong{cost_variance:} How far the task is over or under budget.
#' \item \strong{cost_performance_index:} Relative amount of the variance to
#' Planned Value.
#' \item \strong{estimate_at_completion:} What the overall project budget will
#' be if everything else went according to plan.
#' \item \strong{estimate_to_complete:} How much money must be spent from this
#' point forward, to complete the project.
#' \item \strong{variance_at_completion:} The forecasted cost variance (CV) at
#' the completion of the project.
#' \item \strong{to_complete_performance_index:} What CPI would be necessary
#' to finish the project on budget.
#' }
#' }
#'
#' @examples
#' data(project)
#' earned_value(start = project$start,
#' end = project$end,
#' progress = project$progress,
#' planned_cost = project$planned_cost,
#' project_value = 150000,
#' cost_to_date = 10000,
#' date = "2024-07-03")
#' @export
#'
earned_value <- function(start,
end,
progress,
planned_cost,
project_value,
cost_to_date,
date = today()) {
date <- as.Date(date)
df <- data.frame(start = as.Date(start), end = as.Date(end), progress,
planned_cost) |>
mutate(planned_value =
project_value * .data$planned_cost / sum(.data$planned_cost))
planned_value <- get_planned_value(df)
pos <- which(abs(planned_value$end - date) ==
min(abs(planned_value$end - date)))
tmp <- planned_value$planned_value[pos]
earned_value <- data.frame(date = date,
total_value = project_value,
budget_at_completion = sum(planned_cost),
planned_value = tmp,
earned_value = sum(df$progress * df$planned_value),
actual_cost = cost_to_date)
earned_value <- earned_value |>
mutate(schedule_variance = .data$earned_value - .data$planned_value,
cost_variance = .data$earned_value - .data$actual_cost,
cost_performance_index = .data$earned_value / .data$actual_cost,
estimate_at_completion = project_value /
.data$cost_performance_index,
estimate_to_complete = .data$estimate_at_completion - cost_to_date,
variance_at_completion = .data$budget_at_completion -
.data$estimate_at_completion,
to_complete_performance_index =
(project_value - .data$earned_value) /
(project_value - cost_to_date),
project_complete = .data$earned_value / project_value,
schedule_complete = .data$schedule_variance / project_value)
earned_value <- earned_value[, c("date",
"total_value",
"budget_at_completion",
"project_complete",
"schedule_complete",
"planned_value",
"earned_value",
"actual_cost",
"schedule_variance",
"cost_variance",
"cost_performance_index",
"estimate_at_completion",
"estimate_to_complete",
"variance_at_completion",
"to_complete_performance_index")]
earned_value[-1] <- apply(earned_value[-1], 1, round, digits = 2)
earned_value <- list(pv = planned_value, ev = earned_value)
return(earned_value)
}
Any scripts or data that you put into this service are public.
Add the following code to your website.
For more information on customizing the embed code, read Embedding Snippets.