context("Critican Path on taskdatauncertain3")
library(projmanr)
library(igraph)
library(reshape2)
library(R6)
library(ggplot2)
test_that("Check approximate value of duration mean", {
res <- simulation(projmanr::taskdatauncertain3, 1000)
expect_equal(mean(res$durations) > 38 && mean(res$durations) < 42, TRUE)
})
test_that("Check the return size of simulation", {
res <- simulation(projmanr::taskdatauncertain3, 100)
expect_equal(length(res), 3)
expect_equal(length(res$durations), 100)
expect_equal(nrow(res$critical_indexes), 13)
# Run the same tests, change the itr parameter to
# ensure that it's working
res <- simulation(projmanr::taskdatauncertain3, 1000)
expect_equal(length(res), 3)
expect_equal(length(res$durations), 1000)
expect_equal(nrow(res$critical_indexes), 13)
})
test_that("Make sure the the error check on distribution works", {
temp <- projmanr::taskdatauncertain3
temp[12, 5] <- "t"
expect_error(simulation(temp, 100), paste("Distribution t not supported,",
"please use triangle, pert,",
"uniform, normal or log_normal"))
})
# The following are the same tests from 'testtaskdata3.R'
# ensuring that the introduction of the uncertain columns did
# not cause any issues
test_that("Correct critical path", {
res <- critical_path(projmanr::taskdatauncertain3)
expect_equal(length(res$critical_path), 8)
expect_equal(res$critical_path, c("2", "3", "6", "7",
"9", "10", "11", "13"))
expect_equal(length(res), 5)
expect_equal(res$total_duration, 40)
expect_equal(nrow(res$results), nrow(projmanr::taskdatauncertain3))
})
test_that("Correct critical path is computed with gantt", {
res <- critical_path(projmanr::taskdatauncertain3, gantt = T)
expect_equal(length(res$critical_path), 8)
expect_equal(res$critical_path, c("2", "3", "6", "7",
"9", "10", "11", "13"))
expect_equal(length(res), 6)
expect_equal(res$total_duration, 40)
expect_equal(nrow(res$results), nrow(projmanr::taskdatauncertain3))
})
test_that("Correct critical path is computed with network diagram", {
res <- critical_path(projmanr::taskdatauncertain3, network = T)
expect_equal(length(res$critical_path), 8)
expect_equal(res$critical_path, c("2", "3", "6", "7",
"9", "10", "11", "13"))
expect_equal(length(res), 6)
expect_equal(res$total_duration, 40)
expect_equal(nrow(res$results), nrow(projmanr::taskdatauncertain3))
})
test_that("Correct critical path is computed with both graph", {
res <- critical_path(projmanr::taskdatauncertain3, gantt = T, network = T)
expect_equal(length(res$critical_path), 8)
expect_equal(res$critical_path, c("2", "3", "6", "7",
"9", "10", "11", "13"))
expect_equal(length(res), 7)
expect_equal(res$total_duration, 40)
expect_equal(nrow(res$results), nrow(projmanr::taskdatauncertain3))
})
test_that("Date output is working correctly", {
res <- critical_path(projmanr::taskdatauncertain3, gantt = T, network = T,
start_date = "2017-10-10")
expect_equal(res$end_date, as.Date("2017-11-19"))
res <- critical_path(projmanr::taskdatauncertain3, gantt = T, network = T)
expect_equal(res$end_date, Sys.Date() + 40)
})