#' Add Activities
#'
#' Combine several vectors for activities and their attributes into a tibble,
#' which can be combined with other similarly-generated tibbles, resulting
#' in unique tibble to be added in a schedule. If the schedule already
#' contain some activities, the new activities will be added in the end.
#'
#' A activity tibble, or atb, has at least the following columns:
#'
#' - `id` (of type `integer`): Activity id.
#' It is an integer number that must be unique within a schedule.
#'
#' - `name` (of type `character`): Activity name. It may be empty string.
#'
#' - `duration` (of type `integer`): Activity duration.
#' It is integer number without unit time. It may be zero.
#'
#' An arbitrary number of additional columns containing data attributes
#' can be part of the atb, so long as they follow the aforementioned columns.
#'
#' @param sch A schedule object.
#' @param id Activity id that will be used to make
#' relation between activities. It must be unique.
#' @param name The name of activity.
#' @param duration A number that represents the activity's duration.
#' It must be equal or greater than zero.
#' @param ... One or more vectors for associated activity attributes.
#'
#' @return A schedule with a activity tibble (atb) added.
#'
#' @seealso [sch_reference()], [sch_add_relations()], [sch_add_activity()],
#' [sch_title()], [sch_nr_activities()], [sch_new()], [sch_plan()],
#' [sch_get_activity()], [sch_has_any_activity()],
#' [sch_change_activities_duration()].
#'
#' @examples
#' # Example #1
#' sch <- sch_new() %>%
#' sch_add_activities(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L)
#' ) %>%
#' sch_plan()
#' sch_duration(sch)
#' sch_activities(sch)
#'
#' # Example #2
#' sch <- sch_new() %>%
#' sch_add_activities(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L),
#' resource = "Rubens",
#' cost = 123.45
#' ) %>%
#' sch_plan()
#' sch_duration(sch)
#' atb <- sch_activities(sch)
#' atb$resource
#' atb$cost
#'
#' # Example #3
#' sch <- sch_new() %>%
#' sch_add_activities(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L),
#' resource = c(
#' "Rubens", "Jose", "Rosa", "Rodrigues", "Silva",
#' "Rubens", "Jose", "Rosa", "Rodrigues", "Silva",
#' "Rubens", "Jose", "Rosa", "Rodrigues", "Silva",
#' "Rubens", "Jose"),
#' cost = c(
#' 123.45, 234.56, 345.56, 456.78, 567.89,
#' 123.45, 234.56, 345.56, 456.78, 567.89,
#' 123.45, 234.56, 345.56, 456.78, 567.89,
#' 123.45, 234.56)
#' ) %>%
#' sch_plan()
#' sch_duration(sch)
#' atb <- sch_activities(sch)
#' atb$resource
#' atb$cost
#'
#' @export
sch_add_activities <- function(sch, id, name, duration, ...) {
cpt_assert_schedule_object_valid(sch)
# Validation: vector id must be an integer.
if (!(inherits(id, "integer"))) {
stop("The value supplied to `id` must be integer!")
}
nr_activities <- length(id)
if (nr_activities == 0) {
stop("There is no activity to be included!")
}
# Validation: vector duration must be an integer.
if (!(inherits(duration, "integer"))) {
stop("The value supplied to `duration` must be integer!")
}
# Name validation / treatment
if (is.null(name)) {
name <- as.character(id)
} else if(length(name) != nr_activities) {
stop("The length of `name` must be equal `id`'s length!")
}
# Duration validation
if(length(duration) == 1L) {
duration %<>% rep(nr_activities)
} else if(length(duration) != nr_activities) {
stop("The length of `duration` must be equal `id`'s length!")
}
activities_tib <- tibble::tibble(
id = id,
name = name,
duration = duration,
milestone = FALSE,
critical = FALSE,
early_start = NA_integer_,
early_finish = NA_integer_,
late_start = NA_integer_,
late_finish = NA_integer_,
total_float = NA_integer_,
free_float = NA_integer_
)
extras <- list(...)
extras <- cpt_collect_extra_vectors(nr_activities, extras)
if (inherits(extras, "tbl_df")) {
activities_tib %<>% dplyr::bind_cols(extras)
}
if(sch$info$nr_activities > 0) {
activities_tib <- dplyr::bind_rows(sch$activities, activities_tib)
}
sch$info$status <- "SOME_ACTIVITY"
sch$activities <- activities_tib
sch$info$nr_activities <- nrow(activities_tib)
sch$info$has_any_activity = TRUE
return(sch)
}
#' Add Activity
#'
#' Add an activity and her relations to a schedule. The relations are optional.
#' They will be included if a set of activity id is informed,
#' after activity duration.
#'
#' @param sch A schedule object.
#' @param id Activity id that will be used to make
#' relation between activities. It must be unique.
#' @param name The name of activity.
#' @param duration A number that represents the activity's duration.
#' It must be equal or greater than zero.
#' @param ... A set of activity id relation such that will be linked with
#' activity id. It may be relations of successor or predecessors.
#' @param direction Direction of relations: It may be "succ" or "pred".
#' - `succ`: The relations_id will be the successor of the activity.
#' - `pred`: The relations_id will be the predecessor of the activity.
#'
#' @return A Schedule object with an activity added to it.
#' If relations id is present, it will be included to the schedule.
#'
#' @seealso [sch_change_activities_duration()], [sch_has_any_activity()],
#' [sch_new()], [sch_add_activities()], [sch_get_activity()], [sch_plan()],
#' [sch_nr_activities()], [sch_add_relation()].
#'
#' @examples
#' # Example #1: Only with activities
#' sch <- sch_new() %>%
#' sch_add_activity(1L, "Task 1", 5L) %>%
#' sch_add_activity(2L, "Task 2", 6L) %>%
#' sch_add_activity(3L, "Task 3", 8L) %>%
#' sch_add_activity(4L, "Task 4", 6L) %>%
#' sch_add_activity(5L, "Task 5", 9L) %>%
#' sch_add_activity(6L, "Task 6", 3L) %>%
#' sch_add_activity(7L, "Task 7", 4L) %>%
#' sch_plan()
#' sch_duration(sch)
#' sch_activities(sch)
#'
#' # Example #2: With activities and relations.
#' sch <- sch_new() %>%
#' sch_add_activity(1L, "Task 1", 5L, 2L, 3L) %>%
#' sch_add_activity(2L, "Task 2", 6L, 4L) %>%
#' sch_add_activity(3L, "Task 3", 8L, 5L) %>%
#' sch_add_activity(4L, "Task 4", 6L, 6L) %>%
#' sch_add_activity(5L, "Task 5", 9L, 6L) %>%
#' sch_add_activity(6L, "Task 6", 3L, 7L) %>%
#' sch_add_activity(7L, "Task 7", 4L) %>%
#' sch_plan()
#' sch_duration(sch)
#' sch_activities(sch)
#' sch_relations(sch)
#'
#'
#' @export
sch_add_activity <- function(sch, id, name, duration, ..., direction = "succ") {
relations_id <- list(...)
n <- length(relations_id)
sch %<>%
sch_add_activities(
id = id,
name = name,
duration = duration
)
if(n == 0) {
return(sch)
}
if(direction != "succ" && direction != "pred") {
msg <- base::paste(
"Invalid '", direction, "' direction!",
"It must be 'succ' or 'pred'!"
)
stop(msg)
}
relations_id %<>%
unlist() %>%
as.integer()
if(direction == "succ") {
return(
sch %>% sch_add_relations(
from = id,
to = relations_id
)
)
}
return(
sch %>% sch_add_relations(
from = relations_id,
to = id
)
)
}
#' Add Activities Tibble
#'
#' Add activities tibble to a schedule.
#'
#' @param sch A schedule object.
#'
#' @param atb A tibble with activities definitions.
#'
#' @return A schedule with a activity tibble (atb) added.
#'
#' @examples
#' atb <- tibble::tibble(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L)
#' )
#' sch <- sch_new() %>%
#' sch_add_activities_tibble(atb) %>%
#' sch_plan()
#' sch_duration(sch) #4
#' # sch_activities(sch)
#'
#' @export
sch_add_activities_tibble <- function(sch, atb) {
return(
sch %>% sch_add_activities(
id = atb$id,
name = atb$name,
duration = atb$duration
)
)
}
#' Get Activity
#'
#' Gets an activity by id.
#'
#' @param sch A schedule object.
#' @param aid An activity id as defined by the user.
#'
#' @return A an activity information in a tibble with one line,
#' or an error if activity id doesn't exist.
#'
#' @seealso [sch_activities()], [sch_duration()], [sch_nr_activities()],
#' [sch_add_activities()], [sch_critical_activities()], [sch_has_any_activity()],
#' [sch_change_activities_duration()], [sch_add_activity()].
#'
#' @examples
#' sch <- sch_new() %>%
#' sch_add_activities(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L)
#' ) %>%
#' sch_plan()
#' sch_get_activity(sch, 7)
#'
#' @export
sch_get_activity <- function(sch, aid) {
id <- NULL
act <- sch_activities(sch) %>%
dplyr::filter(id == aid)
if(nrow(act) == 1) {
return(act)
}
stop("Activity 'aid' must exist em activities list!")
}
#' Change Activities Duration
#'
#' Change activities duration and calculates critical path.
#' This way is faster than creating a new schedule with new durations.
#' The order of duration is the insertion order of activities.
#'
#' @param sch A schedule object.
#' @param new_durations A vector with new activities' duration.
#'
#' @return A schedule object with new durations.
#'
#' @seealso [sch_activities()], [sch_has_any_activity()], [sch_duration()],
#' [sch_nr_activities()], [sch_add_activity()], [sch_add_activities()],
#' [sch_get_activity()].
#'
#' @examples
#' sch <- sch_new() %>%
#' sch_title("Project 2: Patient Transport System") %>%
#' sch_reference(
#' "VANHOUCKE, Mario. Integrated project management and control:
#' first comes the theory, then the practice. Gent: Springer, 2014, p. 9") %>%
#' sch_add_activities(
#' id = 1:17,
#' name = paste("a", as.character(1:17), sep=""),
#' duration = c(1L,1L,3L,2L, 2L,2L,2L,1L, 4L,5L,3L,3L, 4L,5L,1L,5L,2L)
#' ) %>%
#' sch_add_relations(
#' from = c(1L, 2L, 3L, 3L, 4L, 5L, 6L, 7L, 8L, 8L, 8L,
#' 8L, 8L, 9L, 10L, 11L, 12L, 13L, 13L, 14L, 14L, 15L, 15L),
#' to = c(2L, 3L, 4L, 6L, 5L, 8L, 7L, 8L, 9L, 10L, 11L,
#' 12L, 13L, 14L, 14L, 14L, 14L, 14L, 15L, 16L, 17L, 16L, 17L)
#' ) %>%
#' sch_plan()
#'
#' # Project duration
#' sch_duration(sch) # 25
#' # Activities duration
#' atb <- sch_activities(sch)
#' atb$duration
#'
#' # Now, change activities duration
#' new_durations <- c(1L,2L,5L, 4L,3L, 2L,1L, 5L, 3L,5L,5L,3L,4L, 2L,1L, 2L,4L)
#' sch %<>%
#' sch_change_activities_duration(new_durations)
#'
#' #Project duration
#' sch_duration(sch) # 31
#' # Activities duration
#' atb <- sch_activities(sch)
#' atb$duration
#'
#' @export
sch_change_activities_duration <- function(sch, new_durations) {
cpt_assert_schedule_object_valid(sch)
# => Verificar se está no STATUS CREATED
if(!cpt_is_schedule_created(sch)) {
stop("To change duration, schedule must be created!")
}
# Validation: vector duration must be an integer.
if (!(inherits(new_durations, "integer"))) {
stop("The value supplied to `new_durations` must be integer!")
}
# Duration validation
if(length(new_durations) != sch_nr_activities(sch)) {
stop("The length of `new_durations` must be equal to `nr_activities`!")
}
if(any(is.null(new_durations) | is.na(new_durations))) {
stop("Error: could not contain NULL or NA duration!")
}
sch$activities$duration <- new_durations
return(cpt_calculate_critical_path(sch))
}
#' Has Any Activity
#'
#' A logical value that indicates if the schedule has any activity.
#' A TRUE value means that the schedule has any activity;
#' a FALSE, means that the schedule do not have any activity.
#'
#' @param sch A schedule object.
#'
#' @return A logical value:
#' - TRUE: The schedule has any activity;
#' - FALSE: The schedule do not have any activity.
#'
#' @seealso [sch_nr_activities()], [sch_critical_activities()],
#' [sch_add_activities()], [sch_change_activities_duration()],
#' [sch_activities()], [sch_nr_relations()], [sch_has_any_relation()],
#' [sch_add_activity()].
#'
#' @examples
#' sch <- sch_new()
#' sch_has_any_activity(sch) # FALSE
#'
#' sch <- sch_new() %>%
#' sch_add_activity(1L, "Only one", 0L) %>%
#' sch_plan()
#' sch_has_any_activity(sch) # TRUE
#'
#' @export
sch_has_any_activity <- function(sch) {
return(sch$info$has_any_activity)
}
#' Nr. of Activities
#'
#' Number of activities in a schedule as an integer value.
#'
#' @param sch A schedule object.
#'
#' @return A integer value indicating the number of activities.
#'
#' @seealso [sch_add_activity()], [sch_nr_relations()], [sch_add_activities()],
#' [sch_activities()], [sch_change_activities_duration()],
#' [sch_critical_activities()], [sch_get_activity()], [sch_has_any_relation()].
#'
#' @examples
#' sch <- sch_new()
#' sch_nr_activities(sch) # 0
#'
#' sch <- sch_new() %>%
#' sch_add_activity(1L, "Only one", 0L) %>%
#' sch_plan()
#' sch_nr_activities(sch) # 1
#'
#' @export
sch_nr_activities <- function(sch) {
return(sch$info$nr_activities)
}
#' Activities
#'
#' Return a tibble with all activities of a schedule in an insertion order.
#' These are the main information calculated by CPM.
#'
#' The tibble is formed by following structure:
#' - **id:** Activity id.
#' - **name:** The name of activity.
#' - **duration:** A number that represents the activity's duration.
#' - **milestone:** A milestone is an activity with zero duration.
#' This property indicates if an activity is a milestone or not:
#' \code{TRUE} indicates it is a milestone; \code{FALSE} indicates it is not.
#' - **critical:** A critical activity is one with total float minor or equal
#' to zero. This property indicates if an activity is critical:
#' \code{TRUE} indicates it is critical;
#' \code{FALSE} indicates it is not critical.
#' - **early_start:** Is the earliest start period an activity can begin
#' after its predecessors without violating precedence relation.
#' - **early_finish:** Is the early start plus activity duration.
#' - **late_start:** Is the late finish minus activity duration.
#' - **late_finish:** Is the latest finish an activity can finish
#' before their successors without violating precedence relation.
#' - **total_float:** It is the amount of period an activity can be
#' delayed without violating the project duration. Its formula is:
#' late_start - early_start or late_finish - early_finish
#' - **free_float:** It is the amount of period an activity can be
#' delayed without violating the start time of the successors activities.
#' - **progr_level:** It is the rank of activities counted from begin.
#' The level of the activities that don't have predecessor is one;
#' the level of the other activities, is one plus the maximal level of
#' their predecessor.
#' - **regr_level:** Regressive level is the rank of activities counted
#' from the end. The level of the activities that don't have successor is the
#' maximal progressive level; the level of the other activities,
#' is one minus the minimal level of their successor.
#' - **topo_float:** It is the difference between progressive level
#' and regressive level.
#'
#' @param sch A schedule object.
#'
#' @return A tibble with activities.
#'
#' @seealso [sch_has_any_activity()], [sch_change_activities_duration()],
#' [sch_add_activity()], [sch_nr_activities()], [sch_critical_activities()],
#' [sch_add_activities()], [sch_get_activity()], [sch_duration()].
#'
#' @examples
#' sch <- sch_new() %>%
#' sch_title("Fictitious Project Example") %>%
#' sch_reference("VANHOUCKE, Mario. Measuring time:
#' improving project performance using earned value management.
#' Gent: Springer, 2009, p. 18") %>%
#' sch_add_activity( 1L, "a1" , 0L, 2,3,4) %>%
#' sch_add_activity( 2L, "a2" , 4L, 5) %>%
#' sch_add_activity( 3L, "a3" , 9L, 10) %>%
#' sch_add_activity( 4L, "a4" , 1L, 6) %>%
#' sch_add_activity( 5L, "a5" , 4L, 9) %>%
#' sch_add_activity( 6L, "a6" , 5L, 7) %>%
#' sch_add_activity( 7L, "a7" , 1L, 8,11) %>%
#' sch_add_activity( 8L, "a8" , 7L, 12) %>%
#' sch_add_activity( 9L, "a9" , 8L, 12) %>%
#' sch_add_activity( 10L, "a10", 3L, 12) %>%
#' sch_add_activity( 11L, "a11", 3L, 12) %>%
#' sch_add_activity( 12L, "a12", 0L) %>%
#' sch_plan()
#' sch_activities(sch)
#'
#' @export
sch_activities <- function(sch) {
return(sch$activities)
}
#' Critical Activities
#'
#' Return a tibble with all critical activities of a schedule in an insertion order.
#'
#' @param sch A schedule object.
#'
#' @return A tibble with critical activities.
#'
#' @seealso [sch_get_activity()], [sch_add_activities()], [sch_activities()],
#' [sch_add_activity()], [sch_nr_activities()], [sch_non_critical_activities()],
#' [sch_has_any_activity()].
#'
#' @examples
#' sch <- sch_new() %>%
#' sch_title("Fictitious Project Example") %>%
#' sch_reference("VANHOUCKE, Mario. Measuring time:
#' improving project performance using earned value management.
#' Gent: Springer, 2009, p. 18") %>%
#' sch_add_activity( 1L, "a1" , 0L, 2,3,4) %>%
#' sch_add_activity( 2L, "a2" , 4L, 5) %>%
#' sch_add_activity( 3L, "a3" , 9L, 10) %>%
#' sch_add_activity( 4L, "a4" , 1L, 6) %>%
#' sch_add_activity( 5L, "a5" , 4L, 9) %>%
#' sch_add_activity( 6L, "a6" , 5L, 7) %>%
#' sch_add_activity( 7L, "a7" , 1L, 8,11) %>%
#' sch_add_activity( 8L, "a8" , 7L, 12) %>%
#' sch_add_activity( 9L, "a9" , 8L, 12) %>%
#' sch_add_activity( 10L, "a10", 3L, 12) %>%
#' sch_add_activity( 11L, "a11", 3L, 12) %>%
#' sch_add_activity( 12L, "a12", 0L) %>%
#' sch_plan()
#' sch_critical_activities(sch)
#'
#' @export
sch_critical_activities <- function(sch) {
critical <- NULL
return(
sch %>%
sch_activities() %>%
dplyr::filter(critical)
)
}
#' Non Critical Activities
#'
#' Return a tibble with all non critical activities of a schedule
#' in an insertion order.
#'
#' @param sch A schedule object.
#'
#' @return A tibble with non critical activities.
#'
#' @seealso [sch_get_activity()], [sch_add_activity()], [sch_activities()],
#' [sch_critical_activities()], [sch_has_any_activity()], [sch_nr_activities()],
#' [sch_add_activities()].
#'
#' @examples
#' sch <- sch_new() %>%
#' sch_title("Fictitious Project Example") %>%
#' sch_reference("VANHOUCKE, Mario. Measuring time:
#' improving project performance using earned value management.
#' Gent: Springer, 2009, p. 18") %>%
#' sch_add_activity( 1L, "a1" , 0L, 2,3,4) %>%
#' sch_add_activity( 2L, "a2" , 4L, 5) %>%
#' sch_add_activity( 3L, "a3" , 9L, 10) %>%
#' sch_add_activity( 4L, "a4" , 1L, 6) %>%
#' sch_add_activity( 5L, "a5" , 4L, 9) %>%
#' sch_add_activity( 6L, "a6" , 5L, 7) %>%
#' sch_add_activity( 7L, "a7" , 1L, 8,11) %>%
#' sch_add_activity( 8L, "a8" , 7L, 12) %>%
#' sch_add_activity( 9L, "a9" , 8L, 12) %>%
#' sch_add_activity( 10L, "a10", 3L, 12) %>%
#' sch_add_activity( 11L, "a11", 3L, 12) %>%
#' sch_add_activity( 12L, "a12", 0L) %>%
#' sch_plan()
#' sch_non_critical_activities(sch)
#'
#' @export
sch_non_critical_activities <- function(sch) {
critical <- NULL
return(
sch %>%
sch_activities() %>%
dplyr::filter(!critical)
)
}
Add the following code to your website.