activities <- data.frame(
id = 1:17,
name = paste("a", as.character(1:17), sep=""),
duration = c(1,2,2,4,3,3,3,2,1,1,2,1,1,1,1,2,1)
)
relations <- data.frame(
from = c(1, 1, 2, 2, 2, 3, 3, 3, 3, 4, 5, 6, 7, 8, 9, 10, 11, 11, 12, 12, 13, 13, 14, 14, 15, 15),
to = c(2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 11, 11, 12, 13, 14, 15, 16, 17, 16, 17, 16, 17, 16, 17, 16, 17)
)
vanhoucke2014_project_1 <- function() {
sch <- sch_new() %>%
sch_title("Project 1: Cost Information System") %>%
sch_reference(
"VANHOUCKE, Mario. Integrated project management and control:
first comes the theory, then the practice.
Gent: Springer, 2014, p. 6"
) %>%
sch_add_activities(
id = activities$id,
name = activities$name,
duration = as.integer(activities$duration)
) %>%
sch_add_relations(
from = as.integer(relations$from),
to = as.integer(relations$to)
) %>%
sch_plan()
return(sch)
}
test_that("Creating a ONE activity schedule with ZERO duration", {
sch <- sch_new() %>%
sch_title("A project") %>%
sch_reference("From criticalpath") %>%
sch_add_activities(
id = 1L,
name = "A",
duration = 0L
) %>%
sch_plan()
atb <- sch_activities(sch)
expect_equal(sch_duration(sch), 0)
expect_equal(atb$early_start[1], 0)
expect_equal(atb$early_finish[1], 0)
expect_equal(atb$late_start[1], 0)
expect_equal(atb$late_finish[1], 0)
expect_true(atb$critical[1])
})
test_that("Creating a schedule with ONE activity", {
sch <- sch_new() %>%
sch_title("A project") %>%
sch_reference("From criticalpath") %>%
sch_add_activities(
id = 1L,
name = "A",
duration = 3L
) %>%
sch_plan()
atb <- sch_activities(sch)
expect_equal(sch_duration(sch), 3)
expect_equal(atb$early_start[1], 0)
expect_equal(atb$early_finish[1], 3)
expect_equal(atb$late_start[1], 0)
expect_equal(atb$late_finish[1], 3)
expect_true(atb$critical[1])
})
test_that("Creating a schedule only with activities list, without relations", {
sch <- sch_new() %>%
sch_title("A project") %>%
sch_reference("From criticalpath") %>%
sch_add_activities(
id = c( 1L, 2L, 3L),
name = c("A", "B", "C"),
duration = c( 3L, 2L, 4L)
) %>%
sch_plan()
atb <- sch_activities(sch)
expect_equal(sch_duration(sch), 4)
expect_equal(atb$early_start[1], 0)
expect_equal(atb$early_finish[1], 3)
expect_equal(atb$late_start[1], 1)
expect_equal(atb$late_finish[1], 4)
expect_false(atb$critical[1])
expect_equal(atb$early_start[2], 0)
expect_equal(atb$early_finish[2], 2)
expect_equal(atb$late_start[2], 2)
expect_equal(atb$late_finish[2], 4)
expect_false(atb$critical[2])
expect_equal(atb$early_start[3], 0)
expect_equal(atb$early_finish[3], 4)
expect_equal(atb$late_start[3], 0)
expect_equal(atb$late_finish[3], 4)
expect_true(atb$critical[3])
})
test_that("Schedule duration is 11", {
sch <- vanhoucke2014_project_1()
expect_equal(sch_duration(sch), 11)
})
test_that("Schedule critical activities are identified", {
atb <- vanhoucke2014_project_1() %>%
sch_critical_activities()
critical_activities <- paste0(atb$id, collapse=",")
expected <- paste0(c(1, 2, 4, 11, 16), collapse = ",")
expect_equal(critical_activities, expected)
})
test_that("Schedule NON critical activities are identified", {
atb <- vanhoucke2014_project_1() %>%
sch_non_critical_activities()
non_critical_activities <- paste0(atb$id, collapse=",")
expected <- paste0(c(3, 5, 6, 7, 8, 9, 10, 12, 13, 14, 15, 17), collapse = ",")
expect_equal(non_critical_activities, expected)
})
test_that("Early Start and Early Finish are correct!", {
atb <- vanhoucke2014_project_1() %>%
sch_activities()
expect_equal(atb$early_start[1], 0)
expect_equal(atb$early_finish[1], 1)
expect_equal(atb$early_start[2], 1)
expect_equal(atb$early_finish[2], 3)
expect_equal(atb$early_start[3], 1)
expect_equal(atb$early_finish[3], 3)
expect_equal(atb$early_start[4], 3)
expect_equal(atb$early_finish[4], 7)
expect_equal(atb$early_start[5], 3)
expect_equal(atb$early_finish[5], 6)
expect_equal(atb$early_start[6], 3)
expect_equal(atb$early_finish[6], 6)
expect_equal(atb$early_start[7], 3)
expect_equal(atb$early_finish[7], 6)
expect_equal(atb$early_start[8], 3)
expect_equal(atb$early_finish[8], 5)
expect_equal(atb$early_start[9], 3)
expect_equal(atb$early_finish[9], 4)
expect_equal(atb$early_start[10], 3)
expect_equal(atb$early_finish[10], 4)
expect_equal(atb$early_start[11], 7)
expect_equal(atb$early_finish[11], 9)
expect_equal(atb$early_start[12], 6)
expect_equal(atb$early_finish[12], 7)
expect_equal(atb$early_start[13], 5)
expect_equal(atb$early_finish[13], 6)
expect_equal(atb$early_start[14], 4)
expect_equal(atb$early_finish[14], 5)
expect_equal(atb$early_start[15], 4)
expect_equal(atb$early_finish[15], 5)
expect_equal(atb$early_start[16], 9)
expect_equal(atb$early_finish[16], 11)
expect_equal(atb$early_start[17], 9)
expect_equal(atb$early_finish[17], 10)
})
test_that("Late Start and Late Finish are correct!", {
atb <- vanhoucke2014_project_1() %>%
sch_activities()
expect_equal(atb$late_start[1], 0)
expect_equal(atb$late_finish[1], 1)
expect_equal(atb$late_start[2], 1)
expect_equal(atb$late_finish[2], 3)
expect_equal(atb$late_start[3], 3)
expect_equal(atb$late_finish[3], 5)
expect_equal(atb$late_start[4], 3)
expect_equal(atb$late_finish[4], 7)
expect_equal(atb$late_start[5], 4)
expect_equal(atb$late_finish[5], 7)
expect_equal(atb$late_start[6], 4)
expect_equal(atb$late_finish[6], 7)
expect_equal(atb$late_start[7], 5)
expect_equal(atb$late_finish[7], 8)
expect_equal(atb$late_start[8], 6)
expect_equal(atb$late_finish[8], 8)
expect_equal(atb$late_start[9], 7)
expect_equal(atb$late_finish[9], 8)
expect_equal(atb$late_start[10], 7)
expect_equal(atb$late_finish[10], 8)
expect_equal(atb$late_start[11], 7)
expect_equal(atb$late_finish[11], 9)
expect_equal(atb$late_start[12], 8)
expect_equal(atb$late_finish[12], 9)
expect_equal(atb$late_start[13], 8)
expect_equal(atb$late_finish[13], 9)
expect_equal(atb$late_start[14], 8)
expect_equal(atb$late_finish[14], 9)
expect_equal(atb$late_start[15], 8)
expect_equal(atb$late_finish[15], 9)
expect_equal(atb$late_start[16], 9)
expect_equal(atb$late_finish[16], 11)
expect_equal(atb$late_start[17], 10)
expect_equal(atb$late_finish[17], 11)
})
test_that("Brings the activities data frame!", {
atb <- vanhoucke2014_project_1() %>%
sch_activities()
expected <- activities
expect_identical(atb$id, expected$id)
})
test_that("Brings the relations data frame!", {
rtb <- vanhoucke2014_project_1() %>%
sch_relations("insert")
expected <- relations
expect_identical(rtb$from, as.integer(expected$from))
expect_identical(rtb$to, as.integer(expected$to))
})