## ---- include = FALSE---------------------------------------------------------
knitr::opts_chunk$set(
collapse = TRUE,
comment = "#>"
)
## ----setup--------------------------------------------------------------------
library(criticalpath)
## -----------------------------------------------------------------------------
sch <- sch_new() %>%
sch_title("Project 1: Cost Information System") %>%
sch_reference("VANHOUCKE, Mario.
Integrated project management and control:
first comes the theory, then the practice.
Gent: Springer, 2014, p. 6") %>%
sch_add_activities(
id = 1:17,
name = paste("a", as.character(1:17), sep=""),
duration = c(1L,2L,2L,4L,3L,3L,3L,2L,1L,1L,2L,1L,1L,1L,1L,2L,1L)
) %>%
sch_add_relations(
from = c(1L, 1L, 2L, 2L, 2L, 3L, 3L, 3L, 3L, 4L, 5L, 6L,
7L, 8L, 9L, 10L, 11L, 11L, 12L, 12L, 13L, 13L, 14L, 14L, 15L, 15L),
to = c(2L, 3L, 4L, 5L, 6L, 7L, 8L, 9L, 10L, 11L, 11L, 11L,
12L, 13L, 14L, 15L, 16L, 17L, 16L, 17L, 16L, 17L, 16L, 17L, 16L, 17L)
) %>%
sch_plan()
sch_duration(sch)
sch_activities(sch)
sch_relations(sch)
## -----------------------------------------------------------------------------
sch <- sch_new() %>%
sch_title("Project 3: Old Carriage House Renovation") %>%
sch_reference(
"VANHOUCKE, Mario. Integrated project management and control:
first comes the theory, then the practice. Gent: Springer, 2014, p. 11") %>%
sch_add_activity( 1L, "a1" , 2L) %>%
sch_add_activity( 2L, "a2" , 2L) %>%
sch_add_activity( 3L, "a3" , 4L) %>%
sch_add_activity( 4L, "a4" , 3L) %>%
sch_add_activity( 5L, "a5" , 4L) %>%
sch_add_activity( 6L, "a6" , 1L) %>%
sch_add_activity( 7L, "a7" , 1L) %>%
sch_add_activity( 8L, "a8" , 1L) %>%
sch_add_activity( 9L, "a9" , 1L) %>%
sch_add_activity(10L, "a10", 1L) %>%
sch_add_activity(11L, "a11", 3L) %>%
sch_add_activity(12L, "a12", 2L) %>%
sch_add_activity(13L, "a13", 1L) %>%
sch_add_activity(14L, "a14", 1L) %>%
sch_add_activity(15L, "a15", 2L) %>%
sch_add_activity(16L, "a16", 1L) %>%
sch_add_activity(17L, "a17", 1L) %>%
sch_add_relation( 1L, 2L) %>%
sch_add_relation( 2L, 3L) %>%
sch_add_relation( 3L, 4L) %>%
sch_add_relation( 4L, 5L) %>%
sch_add_relation( 5L, 6L) %>%
sch_add_relation( 6L, 7L) %>%
sch_add_relation( 6L, 8L) %>%
sch_add_relation( 6L, 9L) %>%
sch_add_relation( 7L, 10L) %>%
sch_add_relation( 8L, 10L) %>%
sch_add_relation( 9L, 10L) %>%
sch_add_relation(10L, 11L) %>%
sch_add_relation(10L, 13L) %>%
sch_add_relation(11L, 12L) %>%
sch_add_relation(12L, 15L) %>%
sch_add_relation(13L, 14L) %>%
sch_add_relation(14L, 15L) %>%
sch_add_relation(15L, 16L) %>%
sch_add_relation(16L, 17L) %>%
sch_plan()
sch_duration(sch)
sch_activities(sch)
sch_relations(sch)
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity(10L, "a10", 3L, 12L) %>%
sch_add_activity(11L, "a11", 3L, 12L) %>%
sch_add_activity(12L, "a12", 0L) %>%
sch_plan()
sch_duration(sch)
sch_activities(sch)
sch_relations(sch)
## -----------------------------------------------------------------------------
# Activities added one by one
sch <- sch_new() %>%
sch_add_activity(1L, "Task 1", 5L) %>%
sch_add_activity(2L, "Task 2", 6L) %>%
sch_add_activity(3L, "Task 3", 8L) %>%
sch_add_activity(4L, "Task 4", 6L) %>%
sch_add_activity(5L, "Task 5", 9L) %>%
sch_add_activity(6L, "Task 6", 3L) %>%
sch_add_activity(7L, "Task 7", 4L) %>%
sch_plan()
sch_duration(sch)
sch_activities(sch)
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
# Add activities and relations to it.
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity( 10L, "a10", 3L, 12L) %>%
sch_add_activity( 11L, "a11", 3L, 12L) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
sch_title(sch)
sch_reference(sch) %>% cat()
sch_duration(sch)
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18")
sch_has_any_activity(sch) # FALSE
sch_nr_activities(sch) # 0
# Add activities and relations to it.
sch %<>%
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity( 10L, "a10", 3L, 12L) %>%
sch_add_activity( 11L, "a11", 3L, 12L) %>%
sch_add_activity( 12L, "a12", 0L) %>%
sch_plan()
sch_has_any_activity(sch) # TRUE
sch_nr_activities(sch) # 12
sch_get_activity(sch, 10L)
sch_activities(sch)
## -----------------------------------------------------------------------------
sch <- sch_new() %>%
sch_title("A project") %>%
sch_reference("From criticalpath") %>%
sch_add_activities(
id = c( 1L, 2L, 3L, 4L ),
name = c("A", "B", "C", "D"),
duration = c( 2L, 3L, 1L, 2L )
) %>%
sch_add_relations(
from = c(1L, 2L, 4L, 4L),
to = c(3L, 3L, 1L, 2L)
) %>%
sch_plan()
gantt <- sch_gantt_matrix(sch)
gantt
# What is the effort by time period?
colSums(gantt) # 1 1 2 2 1 1
# What is the duration by activities?
rowSums(gantt) # 2 3 1 2
# what is the S curve
cumsum(colSums(gantt))
plot(cumsum(colSums(gantt)), type="l", lwd=3)
xyw <- sch_xy_gantt_matrix(sch)
xyw
plot(xyw[, 1:2])
## -----------------------------------------------------------------------------
sch <- sch_new() %>%
sch_title("Project 2: Patient Transport System") %>%
sch_reference(
"VANHOUCKE, Mario. Integrated project management and control:
first comes the theory, then the practice. Gent: Springer, 2014, p. 9") %>%
sch_add_activities(
id = 1:17,
name = paste("a", as.character(1:17), sep=""),
duration = c(1L,1L,3L,2L, 2L,2L,2L,1L, 4L,5L,3L,3L, 4L,5L,1L,5L,2L)
) %>%
sch_add_relations(
from = c(1L, 2L, 3L, 3L, 4L, 5L, 6L, 7L, 8L, 8L, 8L,
8L, 8L, 9L, 10L, 11L, 12L, 13L, 13L, 14L, 14L, 15L, 15L),
to = c(2L, 3L, 4L, 6L, 5L, 8L, 7L, 8L, 9L, 10L, 11L,
12L, 13L, 14L, 14L, 14L, 14L, 14L, 15L, 16L, 17L, 16L, 17L)
) %>%
sch_plan()
#Project duration
sch_duration(sch) # 25
#Activities duration
sch_activities(sch)$duration
new_durations <- c(1L,2L,5L, 4L,3L, 2L,1L, 5L, 3L,5L,5L,3L,4L, 2L,1L, 2L,4L)
sch %<>%
sch_change_activities_duration(new_durations)
#Project duration
sch_duration(sch) # 31
#Activities duration
sch_activities(sch)$duration
## -----------------------------------------------------------------------------
n <- sch %>% sch_nr_activities()
set.seed(45678)
i <- sample(n)
another_schedule <- sch_new() %>%
sch_add_activities(
id = sch_activities(sch)$id[i],
name = sch_activities(sch)$name[i],
duration = sch_activities(sch)$duration[i]
) %>%
sch_add_relations(
from = c(1L, 2L, 3L, 3L, 4L, 5L, 6L, 7L, 8L, 8L, 8L,
8L, 8L, 9L, 10L, 11L, 12L, 13L, 13L, 14L, 14L, 15L, 15L),
to = c(2L, 3L, 4L, 6L, 5L, 8L, 7L, 8L, 9L, 10L, 11L,
12L, 13L, 14L, 14L, 14L, 14L, 14L, 15L, 16L, 17L, 16L, 17L)
) %>%
sch_plan()
another_schedule %<>% sch_change_activities_duration(new_durations[i])
# Second schedule.
sch_duration(another_schedule)
# First schedule.
sch_duration(sch)
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18")
sch_has_any_relation(sch) # FALSE
sch_nr_relations(sch) # 0
sch %<>%
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity(10L, "a10", 3L, 12L) %>%
sch_add_activity(11L, "a11", 3L, 12L) %>%
sch_add_activity(12L, "a12", 0L) %>%
sch_plan()
sch_has_any_relation(sch) # TRUE
sch_nr_relations(sch) # 14
sch_relations(sch)
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
sch_add_activity( 2L, "a2" , 4L, 5L, 12L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity(10L, "a10", 3L, 12L) %>%
sch_add_activity(11L, "a11", 3L, 12L) %>%
sch_add_activity(12L, "a12", 0L) %>%
sch_plan()
sch_all_successors(sch, 2) # 5, 9, 12
sch_all_successors(sch, 7) # 8, 11, 12
sch_all_successors(sch, 10) # 12
sch_successors(sch, 2) # 5, 12
sch_successors(sch, 7) # 8, 11
sch_successors(sch, 10) # 12
sch_all_predecessors(sch, 2) # nothing
sch_all_predecessors(sch, 7) # 6, 4
sch_all_predecessors(sch, 10) # 3
sch_predecessors(sch, 2) # nothing
sch_predecessors(sch, 7) # 6
sch_predecessors(sch, 10) # 3
sch_is_redundant(sch, 2, 5) #FALSE
sch_is_redundant(sch, 2, 12) #TRUE
## -----------------------------------------------------------------------------
# Create a schedule
sch <- sch_new() %>%
sch_title("Fictitious Project Example") %>%
sch_reference("VANHOUCKE, Mario. Measuring time:
improving project performance using earned value management.
Gent: Springer, 2009, p. 18") %>%
# Add activities and relations to it.
sch_add_activity( 1L, "a1" , 0L, 2L,3L,4L) %>%
sch_add_activity( 2L, "a2" , 4L, 5L) %>%
sch_add_activity( 3L, "a3" , 9L, 10L) %>%
sch_add_activity( 4L, "a4" , 1L, 6L) %>%
sch_add_activity( 5L, "a5" , 4L, 9L) %>%
sch_add_activity( 6L, "a6" , 5L, 7L) %>%
sch_add_activity( 7L, "a7" , 1L, 8L,11L) %>%
sch_add_activity( 8L, "a8" , 7L, 12L) %>%
sch_add_activity( 9L, "a9" , 8L, 12L) %>%
sch_add_activity(10L, "a10", 3L, 12L) %>%
sch_add_activity(11L, "a11", 3L, 12L) %>%
sch_add_activity(12L, "a12", 0L) %>%
sch_plan()
sch_topoi_sp(sch)
sch_topoi_ad(sch)
sch_topoi_la(sch)
sch_topoi_tf(sch)