R/tpr.r

Defines functions tpr

Documented in tpr

#-----------------------------------------------------------------------------#
#                                                                             #
#  MATRIX-BASED FLEXIBLE PROJECT PLANNING                                     #
#                                                                             #
#  Written by: Zsolt T. Kosztyan, Aamir Saghir                                #
#              Department of Quantitative Methods                             #
#              University of Pannonia, Hungary                                #
#              kosztyan.zsolt@gtk.uni-pannon.hu                               #
#                                                                             #
# Last modified: June 2024                                                    #
#-----------------------------------------------------------------------------#

#' @export
#' @importFrom graphics par barplot axis legend
#' @importFrom stats na.omit rbeta
#' @importFrom utils tail
tpr<- function(SST,DSM,TD,RD,res.graph=FALSE)
{
  if (!requireNamespace("pracma", quietly = TRUE)) {
    stop(
      "Package \"pracma\" must be installed to use this function.",
      call. = FALSE
    )
  }
  if (!requireNamespace("Rfast", quietly = TRUE)) {
    stop(
      "Package \"Rfast\" must be installed to use this function.",
      call. = FALSE
    )
  }
  if (!requireNamespace("Matrix", quietly = TRUE)) {
    stop(
      "Package \"Matrix\" must be installed to use this function.",
      call. = FALSE
    )
  }
  SST[is.na(SST)]<-0
  N <-pracma::numel(SST)               #Number of tasks
  DSM <-round(pracma::triu(DSM))       #DSM must be an upper triangular binary matrix.
  DSM[(matrix(diag(DSM)==0)*1),]<-0    #Excluded task has no dependency
  DSM[,(matrix(diag(DSM)==0)*1)]<-0    #Excluded task has no dependency
  TD[matrix(diag(DSM)==0)*1]<-0        #Excluded task has no time demands
  RD[(matrix(diag(DSM)==0)*1),]<-0     #Excluded task has no resources
  RD[is.nan(RD)]<-0
  SST[matrix(diag(DSM)==0)*1]<-0       #Excluded task's start time is zero
  SST<-matrix(SST)                     #SST should be a column vector
  n<-pracma::numel(TD)                 #Number of elements in vector T
  SFT<-SST+TD                          #Initialisation
  for (i in 1: (n-1)) {
    for (j in (i+1):n) {
      if (DSM[i,i]> 0)
        if (DSM[j,j]> 0)
          if (DSM[i,j]> 0)             #If there is a dependency between task i and task j.
            if (SST[j] < SFT[i])
            {
              SST[j]<- SFT[i]
              SFT[j]<- SST[j]+TD[j]
            }
    }
  }
  BP<- sort(matrix(union(SST,SFT)))    #Breakpoints, where the resource demands should be recalculated
  b <- pracma::numel(BP)               # Number of breakpoints
  B<- t((pracma::repmat(SST,1,b)<=
           pracma::repmat(BP, N,1))& (pracma::repmat(SFT,1,b)>
                                        pracma::repmat(BP, N,1)))*1
  RESFUNC<- matrix(as.double(B), dim(B)[1], dim(B)[2])%*% RD       #RESFUNC=mtimes(B,R); %Calculate resource function
  rMAX<- Rfast::colMaxs(RESFUNC, value=TRUE)
  H<-t(rMAX)
  colnames(H)<-paste("R",1:ncol(H),sep="_")
  rownames(H)<-"TPR"
  if (res.graph==TRUE){
    TPT<-tpt(DSM,TD,SST)$TPT
    Width=as.vector(matrix(0,1,length(BP)))
    if (length(BP)>1)
      for (i in 2:length(BP)){
        Width[i-1]<-BP[i]-BP[i-1]
      }
    Width[length(BP)]<-TPT-BP[length(BP)]
    m<-pracma::size(RESFUNC,2)
    oldpar<-par(no.readonly = TRUE)
    on.exit(par(oldpar))
    par(mfrow=c(m,1))
    for (i in c(1:m)){
      barplot(RESFUNC[,i],width = Width,space = 0,col = "darkgreen",
              beside =TRUE,border=NA,xlab="Duration",ylab=paste("R",i,sep="_"))
      axis(side=1,at=c(0:TPT))
    }
  }
  return(H)
}